Construction of the Hydrogen Energy Supply Chain (HESC) Project’s Hastings site, in Victoria, Australia, where hydrogen will be liquefied, stored, and loaded onto a ship for export, has been completed.
At the Latrobe Valley coal gasification and refining facility, the end of construction is imminent, and commissioning is underway.
In Latrobe Valley, where coal gasification and gas refining will take place, logistics delays caused by Covid-19 have been managed to minimise impacts on the building timeline.