Electrolyser deliveries to Bad Lauchstädt Energy Park’s 30MW green hydrogen plant near Leipzig, Germany are expected to begin in the second half of 2024.
Nine months after breaking ground on the plant, the Park’s consortium has completed the construction of the electrolysis building shell which will house a 30MW Sunfire alkaline electrolyser system.
With regular operations at the site set to begin at the end of 2025, further structural work will continue on the electrolysis building, with cable shafts and earthworks being completed.